API Support & FAQ

Ask a Question
Back to All

Ability to get hours expected in given window

In Classic LP we had an analytics report that we used to show hours expected to be consumed in a given period (week for example). It had started from a Task report. We could hit this single report with start & end date filters and get the work that 'should' be happening in this window.

Is there a way to query LP New for the same information? As I'm looking at the API, I'm only seeing filters for items based on their expected/target starts & finishes. I don't think this is what I'm looking for as reality might not be what we expected or targeted.

As a disclaimer, I'm not really an LP "user", I'm trying to extract information that our users are maintaining. My grasp of terminology and interconnections may be a little weak.